HP ProLiant DL380 Gene 3 Server High-Density Deployment
29
ration
Connecting Cables
This section discusses connecting and routing cables with different cable management solutions and
different console management solutions.
WARNING: To reduce the risk of serious personal injury, fire, or equipment
damage:
• Unplug the power cord from the system.
• Do not disable the power cord grounding plug. The grounding plug is an
important safety feature.
• Plug the power cord into a grounded (earthed) electric outlet that is easily
accessible at all times.
• Extend only one server at a time. A rack might become unstable if more than
one server is fully extended for any reason.
IMPORTANT: In 7000-series racks, route the power cables from the servers to the PDUs through the gap in
the rear of the rack rail.
In-Rack Local
Console
To install cables with in-rack local consoles:
1. Connect the cables to each device installed in the rack, working from the bottom to the top.
2. Connect the cables to the bottom piece of equipment.
3. Bundle the cables and route them through the cable management solution.
4. Connect the cables to the console switchbox.
5. Connect the power cord to the PDU. Do not connect the PDU to any power source until all
equipment is fully deployed in the rack.
When the cables are properly connected and routed through the cable management solution, the
rear door of the rack closes easily over the cables. If the rear door does not close easily, additional
space may be required. Install the Rack Extension kit (P/N 154392-B21) or bustle kit to provide
more space for the cables at the rear of the rack.
Remote Console
Management
The remote console management system uses a CAT5 cable connected to the RJ-45 connector in the
RILOE II PCI board, as well as the power cord.
1. Route the CAT5 cable and the power cord through the cable management system according to
the instructions in the server documentation.
2. Connect the power cord to the PDU.
3. Connect the CAT5 cable to the network data line outlet.
Completing the
Installation
To complete the installation:
1. Install side panels on the outside of the end racks.
2. Install the front and rear doors.
3. Connect the PDUs to the power source.
4. Power up the servers.