4 Installation and Commissioning
Copyright © Huawei Technologies Co., Ltd.
Load low voltage disconnection (LLVD)
threshold
Battery low voltage disconnection (BLVD)
threshold
4.5 Acceptance Criteria
Install and accept the ESM to ensure that the ESM can work properly.
The indicator status is normal (the RUN indicator is steady on and
no indicator is red).
You are advised to simulate mains disconnection or connection.
The working status of the ESM is normal after the mains
disconnection or connection.
The ESM current is normal. According to system settings, the
current deviation is within ±2 A.