FusionModule5000 Smart Modular Data Center
Maintenance Guide (ECC800)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Fuse of phase L1 of power board 1
Fuse of phase L2 of power board 1
Fuse of phase L3 of power board 1
Fuse of phase L3 of monitoring board 1
Fuse of phase L2 of monitoring board 1
Fuse of phase L1 of monitoring board 1
Fuse of phase L3 of monitoring board 2
Fuse of phase L2 of monitoring board 2
Fuse of phase L1 of monitoring board 2
Fuse of phase L3 of monitoring board 3
Fuse of phase L2 of monitoring board 3
Fuse of phase L1 of monitoring board 3
Table 5-2 Fuse description for the dual-input scenario
Fuse of the yellow indicator of I or II route
Fuse of the green indicator of I or II route
Fuse of the red indicator of I or II route
Fuse of phase L1 of power board 1 or 4
Fuse of phase L2 of power board 1 or 4
Fuse of phase L3 of power board 1 or 4
Fuse of phase L3 of monitoring board 1 or fuse of phase L1 of
monitoring board 4
Fuse of phase L2 of monitoring board 1 or fuse of phase L2 of
monitoring board 4
Fuse of phase L1 of monitoring board 1 or fuse of phase L3 of
monitoring board 4
Fuse of phase L3 of monitoring board 2 or fuse of phase L1 of
monitoring board 5
Fuse of phase L2 of monitoring board 2 or fuse of phase L2 of
monitoring board 5
Fuse of phase L1 of monitoring board 2 or fuse of phase L3 of
monitoring board 5