FusionModule5000 Smart Modular Data Center
Maintenance Guide (ECC800)
5 Parts Replacement
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
188
Material: a new undamaged and undeformed camera of the appropriate model
Procedure
1. Unscrew and remove the front cover from the camera.
Figure 5-88 Removing the front cover from a camera
2. Remove the screws from the camera.
Figure 5-89 Removing a camera
3. Remove the monitoring network cable from the camera and remove the camera.
4. Install the new camera by following the instructions about camera installation in the
ECC800 Data Center Controller User Manual. Configure the camera parameters by
following the instructions about camera commissioning in the ECC800 Data Center
Controller User Manual.