2. Select the new device, choose Running Param. > Adjustment, and set Adjust
total energy yield and Calibration of total power supply from grid to be
the same as those of the original device.
Figure 9-24 Energy yield calibration
Step 6 After the topology is identied successfully, update the Smart PCS software.
Ensure that the software version of the new Smart PCS is the same as that of the
running Smart PCS on site.
Step 7 View the running status of the Smart PCS to check whether the Smart PCS
functions properly.
Step 8 Delete the faulty Smart PCS.
Choose Maintenance > Connect Device, select the faulty Smart PCS, click
Remove Devices, and click Conrm.
Figure 9-25 Deleting a device
Step 9 (Optional) Log in to the Smart PV Management System, enter the PV plant, click
Device Management, select the faulty Smart PCS, click Delete, and click OK.
LUNA2000-200KTL-H0 Smart Power Control System
User Manual 9 Device Maintenance