Huawei LUNA2000 - 6 System Commissioning; Verification before Power-On

Huawei LUNA2000
96 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
6 S
ystem Commissioning
6.1
Verication Before Power-On
Table 6-1 Check items and acceptance criteria
No. Check Item Acceptance Criteria
1 Battery installation The installation is correct and reliable.
2 Cables routing Cables are routed properly as required
b
y the customer.
3 Cable tie Cable ties are evenly distributed and no
burr exists.
4 Grounding The PE cable is connected correctly,
securely, and reliably.
5 Switch The DC switch and all switches
connected to the battery are OFF.
6 Cable connection The AC output power cable, DC input
power cable, battery cable, and signal
cable are connected correctly, securely,
and reliably.
7 Unused terminal and port Unused terminals and ports are locked
by watertight caps.
8 Installation environment The installation space is proper, and
the installation environment is clean
and tidy.
LUNA2000-(5-30)-S0
User Manual 6 System Commissioning