Figure 5-10 Installing the front and rear ends of a holding rail
2. Insert the positioning pins on the rear of the rail into the square holes in the
cabinet. See (3) in Figure 5-10.
3. Align the front with a square hole, and push the holding rail forward until it
snaps into place. See (4) in Figure 5-10.
4. Push the hook backwards so that its metal sheet touches the mounting bar.
See (5) in Figure 5-10.
5. (Optional) Install an M6 screw in the third square hole at the rear of the
holding rail to secure it. See (6) in Figure 5-10.
6. Install the other holding rail in the same way.
Step 2 Install the server.
1. Pull out the inner rails as far as they will go. See Figure 5-11.
TaiShan 200 Server
User Guide (Model 2280) 5 Install and Congure
Issue 04 (2020-01-16) Copyright © Huawei Technologies Co., Ltd. 51