5 Operations
5.1 Checking Before Power-On
AC cable colors comply with local regulations.
The input and output are not short-circuited.
Cables and terminals are securely connected.
Battery cables and terminals are correctly connected. Otherwise, the UPS may
be damaged. Voltages comply with industry standards.
The UPS is properly connected to battery strings.
Power cables and signal cables are correctly labeled.
Cables are neatly routed and securely bound according to requirements.
The equipment is installed and cables are routed in ways that facilitate
modication, capacity expansion, and maintenance.
The equipment is properly grounded.
The voltage
dierence between the neutral wire and the ground cable is less
than 5 V AC.
The mains input voltage ranges from 120 V AC to 280 V AC during power-on.
After the UPS is powered on, the mains input voltage ranges from 80 V AC to
280 V AC. The battery voltage range is as follows: (Number of batteries x 10.8
V DC) to (Number of batteries x 14 V DC).
UPSJZ-T-(1 kVA–3 kVA)
User Manual 5 Operations
2022-08-15 76

Related product manuals