Note:  If  there  is  a  gap  between  the  controller  and  the  retaining  clips,  the 
controller  has  not  been  correctly  installed.  In  this  case,  open  the  retaining  clips 
and  remove  the  controller;  then,  reinsert  the  controller. 
11.  Remove  the  battery  from  the  ServeRAID-8k  SAS  Controller  package. 
12.  Slide  the  battery  mounting  tabs  into  the  battery  mounting  clips  on  the  server 
wall  that  is  next  to  the  ServeRAID  SAS  controller  connector. 
13.  Connect  the  battery  to  the  ServeRAID-8k  SAS  Controller. 
14.  Replace  the  air  baffle  over  the  DIMMs.  See  the  User’s  Guide  for  more 
information. 
15.  Replace  the  riser-card  assembly.
If
  you  have  other  optional  devices  to  install  or  remove,  do  so  now.  Otherwise,  go  to 
“Completing  the  installation.” 
Notes: 
1.  When  you  restart  the  server  for  the  first  time  after  you  install  a  ServeRAID-8k 
SAS  controller,  the  monitor  screen  remains  blank  while  the  controller  initializes 
the  battery.  This  might  take  a  few  minutes,  after  which  the  startup  process 
continues.  This  is  a  one-time  occurrence. 
Important:  You  must  allow  the  initialization  process  to  be  completed.  If  you  do 
not,  the  battery  pack  will  not  work,  and  the  server  might  not  start. 
The  battery  comes  partially  charged,  at  30%  or  less  of  capacity.  Run  the  server 
for  4  to  6  hours  to  fully  charge  the  controller  battery.  The  LED  just  above  the 
battery  on  the  controller  remains  lit  until  the  battery  is  fully  charged. 
Until  the  battery  is  fully  charged,  the  controller  firmware  sets  the  controller 
cache  to  write-through  mode;  after  the  battery  is  fully  charged,  the  controller 
firmware  re-enables  write-back  mode. 
2.  When  you  restart  the  server,  you  will  be  given  the  opportunity  to  import  the 
existing  RAID  configuration  to  the  new  ServeRAID  SAS  controller.
Completing  the  installation 
To  complete  the  installation,  complete  the  following  steps: 
1.  Install  the  cover.  See  “Installing  the  cover”  on  page  33  for  more  information. 
2.  Install  the  server  in  the  rack  cabinet.  See  the  Rack  Installation  Instructions  that 
come  with  the  server  for  detailed  information  about  how  to  install  the  server  in  a 
rack  cabinet. 
 
Attention: 
v  Install  the  server  only  in  a  rack  cabinet  that  has  perforated  doors. 
v  Do  not  leave  open  space  above  or  below  an  installed  server  in  your  rack 
cabinet.  To   help  prevent  damage  to  server  components,  always  install  a  filler 
panel  to  cover  the  open  space  and  to  help  ensure  proper  air  circulation.  See 
the  documentation  that  comes  with  the  rack  cabinet  for  more  information.
3.  Connect  the  cables  and  power  cords. 
 
Attention:  In  a  dc  power  environment,  only  trained  service  personnel  other 
than  IBM  service  technicians  are  authorized  to  connect  or  disconnect  power  to 
the  dc  power  supply.  See  the  documentation  that  comes  with  each  dc  power 
supply.
See
  “Connecting  the  cables”  on  page  33  for  more  information. 
4.  Update  the  server  configuration.  See  “Updating  the  server  configuration”  on 
page  34  for  more  information.
 
32  IBM  System  x3650  Type  7979:  Installation  Guide