Installation
‑65‑
Figure 5‑24 Removing the air filter baffle
5.7.4 Inspection After Installation
After the installation is completed, inspect the items in the following table and tick
compliant items.
Table 5–11 Post‑installation inspection checklist
No. Item
Compliance
1
The anti‑tilt label is contact.
2
The ceiling height meets the minimum requirements (for
smooth ventilation). The air inlet and air outlet are clear of
obstruction and have sufficient space. Sufficient space is
reserved for safe passing with the cabinet door open.
3
The wooden pallets for transportation are removed after the
AC drive is delivered to the installation location.
4
The cabinet is firmly attached to the fixing points provided.
5
All contact protection devices (such as the guard) inside and
outside the cabinet are installed.
5.8 Electrical Installation
5.8.1 Inspection Before Wiring
Complete the following inspection items before wiring.
Table 5–12 Pre‑wiring inspection checklist
No. Item
1
The diameter and shield of the cables used meet corresponding
requirements.
2
The AC drive is properly grounded.