Step 3. Select the first current calibration point. Wait a minimum of 5 minutes for the temperature to
stabilize before measuring the input current and entering the data.
Front Panel Menu Reference SCPI Command
Display shows: “Enter P1 measured data” Calculate the shunt current (I=V/R)
and enter the data.
Press Select when done.
CAL:LEV P1
*OPC?
CAL:DATA <data>
Step 4. Select the second current calibration point. Wait a minimum of 5 minutes for the temperature
to stabilize before measuring the input current and entering the data.
Front Panel Menu Reference SCPI Command
Display shows: “Enter P2 measured data”
Calculate the shunt current (I=V/R) and enter the data.Press Selectwhen
done.Press Next to finish calibration.
CAL:LEV P2
*OPC?
CAL:DATA <data>
6 Verification and Calibration
376 Keysight N6700C Operating and Service Guide