Commissioning
Before switching on
6
l
26
EDS82ZAFIC EN 2.0
6 Commissioning
6.1 Before switching on
( Stop!
Before you switch on the standard device and the plugged−in function module
for the first time, check ...
ƒ the entire wiring for completeness, short circuit and earth fault.
ƒ the setting of the DIP switch S1 ( 29):
Setting for the last node = OFF
Setting for all other nodes = ON