5 Commission the pump
To commission the pump:
1. Make sure that the voltage selection is set to the correct value required
for the application. Refer to Figure: Voltage selection plate.
2. Make sure that all openings to atmospheric pressure in the foreline
vacuum system are closed.
3. Connect the power cord.
4.
Set the mains circuit breaker (Figure: Interface control panel (8)) to ON.
Make sure that the power indicator LED (Figure: Interface control panel
(14)) illuminates. If the LED does not illuminate, contact us.
5. Press the start button (Figure: Interface control panel (1)) until the run
indicator LED (Figure: Interface control panel, (13)) begins to ash.
6. When the dry pumping system starts and continues to operate, if an
alarm condition is indicated:
A. shut down the dry pumping system, refer to Shut down the
pump on page 31.
B. refer to Fault nding on page 51
C. if problem has not been rectied, contact us.
7. After you commission the dry pumping system:
A. to continue to operate the system, refer to Start the pump on
page 31.
B. to shut down the system, refer to Shut down the pump on page
31.