Fire damper - FDMRPage 78 Version 2023-06-15
TPM 140/19
≥ 20
≥ 10
Ø
D
ØD+10
+3
(installation
opening)
X
4 x Ø12
≥ 20
A
A
≥ 10
≥ 10
EIS 90
A-A
100
Ø
D
110
X = ØD+120 for dampers ØD 100-200 mm
X = ØD+167 for dampers ØD 225-800 mm
For connection of following duct → see page 90
Installation frame can be installed on the damper or delivered separately
Installation procedure of the installation frame for FDMR → see manual
Conditions of this installation are also valid for the installation in Solid ceiling construction
In gypsum wall construction - installation next to the wall/ceiling - installation frame R5
1 FDMR
2 Installation frame - apply HILTI CFS-S ACR mastic at the entire area and
glue it to the fire separating construction
3 Fill the gaps with glue PROMAT K84
4 Duct
5 Solid gypsum construction
6 Solid ceiling construction
7 Holes for fixing the frame with threaded rods or steel anchors (frame
fixing material not included)