EasyManuals Logo
Home>McQuay>Controller>MicroTech II

McQuay MicroTech II User Manual

McQuay MicroTech II
136 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #43 background imageLoading...
Page #43 background image
OM 780-2 Page 43
Stage-up with Series-Piped Chillers
Consider the chiller system in Figure 13. A typical sequence order would be to enable chiller 1, then 2, then 3, and finally
4. A problem would occur because chiller 4 would not be enabled by the CSM. Chiller 1 is enabled normally. Chiller 2
will be enabled when chiller 1 reaches full load. On primary-secondary systems, chiller 3 would typically get enabled when
the load requires more flow than the single primary pump supplying chillers 1 and 2 can deliver. After chiller 3 is enabled,
water flow is split between the two sets of series-piped chillers, which also splits the cooling load between the two sets.
Chiller 3 would move to a full load condition but chillers 1 and 2 would both move to partially loaded conditions (roughly
50% load each). Since chillers 1 and 2 never reach full load, the CSM would not stage-up to enable chiller 4, even if the
system required more cooling capacity.
Figure 13. Chiller System with Evaporators Piped in the Series/Parallel Configuration
Chiller #3
Chiller #1 Chiller #2
Chiller #4
Centrifugal
Centrifugal Centrifugal
Centrifugal
When staging-up series-piped chillers, the CSM will automatically enable the second chiller of a series-piped pair 30
seconds after the first was enabled when either of the following conditions already exist in the system.
1. A pair of series-piped chillers are both already enabled
2. Any non-series piped chiller is already enabled
Series-piped chiller pair is already enabled
Condition 1 allows the first and second chillers in Figure 13 to be enabled separately, but once a third chiller is enabled the
forth chiller will automatically be enabled 30 seconds later. A typical chiller system would have a sequence order where
chillers 1 and 2 are the first and second chillers enabled based on run time, and chillers 3 and 4 would be enabled together
when additional flow or additional capacity is required. The table below shows how this typical series-piped system would
be configured and the resulting stage-up sequence.
Table 11. Example of a Typical Sequence Order with Series-Piped Chillers
Chiller # Sequence Number (in Row 1
of the Sequence Order Table on
the Chiller Seq screen)
This Chiller Series-Piped
With Chiller # (variable on
the Chiller Setup screen)
Resulting Sequence Order
1 1 2 First Chiller On = 1 (or 2 based on lowest runtime of 1 or 2)
2 1 1 Second Chiller On = 2 (or 1 based on runtime of 1 or 2)
3 2 4 Third Chiller On = 3 (or 4 based on lowest runtime of 3 or 4)
Forth Chiller is Automatically Enabled 30 seconds after Third
Chiller was Enabled
42 3
Non-series chiller is already enabled
Condition 2 allows for the same type of automatic series-piped pair chiller enabling as condition 1 but allows for systems
with evaporators piped in a combination of the Series/Parallel Configuration and Parallel Configuration. In this case a
single non-series-piped chiller that is already enabled will force both chillers of a series-piped pair to be enabled.

Table of Contents

Other manuals for McQuay MicroTech II

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the McQuay MicroTech II and is the answer not in the manual?

McQuay MicroTech II Specifications

General IconGeneral
BrandMcQuay
ModelMicroTech II
CategoryController
LanguageEnglish

Related product manuals