Operation
Packing products
11.06.2014 45
¾ Insert film pouch.
– The opening of the film pouch should extend 2 to 3 cm beyond
the sealing device.
¾ Gas flushing option: Pull the opening of the film pouch over the
nozzles so that inert gas flows into the film pouch.
¾ Pull the pouch neck flat on the sealing bar.
– The pouch neck lies on the sealing bar without creases.
NOTICE Danger of material damage!
Penetration by foreign matter (e.g. liquids, product residue, foreign
bodies) will damage the vacuum pump.
Damage can cause faults in the machine, which in turn can result in
reject packs.
¾ Cancel the evacuation process immediately if foreign matter is
sucked in.
¾ Change the oil in the vacuum pump.
¾ To start the machine after it has been switched on, firmly press
the opened chamber lid shut against the resistance by pressing
the middle of its front edge.
– The processes in the machine run automatically.
– The chamber lid opens automatically after the packaging pro-
cedure.