Commercial and lndustrial MACH 10
®
Ultrasonic Meter Installation and Maintenance Guide 9
Chapter 3: General Installation Guidelines
This chapter defines tools, materials, and general installation information for the
C&I MACH 10
®
.
Tools and Materials
The following tables show the recommended tools and materials you need to successfully
install the C&I MACH 10 and replace the Unitized Measuring Element (UME).
The tables in this chapter do not contain complete lists of tools and materials.
Item Description / Recommendation Use
Site Work Order Documentation provided by your
utility.
Receiving and recording
information about the work site.
Tool Kit Contains standard tools including:
l Screwdrivers.
l Pliers.
l Socket or open-face wrenches.
l Replacement gaskets.
Performing various installation
procedures.
Spacers (optional) N/A If non-compatible lay length of
replacement meter.
Flashlight N/A Activating the LCD.
Moisture Protection
Compound
Novagard
®
sealant Part No: 96018-
072.
Connecting the pit antenna to the
Meter Interface Unit (MIU).
Magnet l 6 lb force.
l Part No: 12287-0001.
Activating the MIU (if required).
Table 6 – Recommended Tools and Materials for Meter Installation
Item Description / Recommendation Use
Tool Kit Contains standard tools including:
l Screwdrivers.
l ¾" socket or open-face
wrenches.
l Replacement gaskets (provided
with UME kit).
Performing various replacement
procedures as outlined in the
instructions. Note that a ¾" open-face
wrench is required on 3" and 4" R900i
UME replacements for the two bolts
directly under the radio.
Flashlight N/A Activating the LCD.
Table 7 – Recommended Tools for Unitized Measuring Element Replacement