NORDAC SK 200E Manual
80 Subject to technical alterations BU 0200 GB
3.4.6 DeviceNet, SK CU4-DEV
Up to four connected frequency inverters can be managed by the internal DeviceNet module via DeviceNet
(control, status messages, parameterisation and diagnosis).
Baud rate: Max. 500 kBaud
Protocol: AC-Drive and NORD-AC
2x digital inputs
DIP switches for: addressing, baud rate
Status LEDs: Module status, module error, bus
status, bus error, Dig. In 1, Dig. In 2
The terminal block of the Customer Unit SK CU4-DEV is divided into two potential levels.
Up to 2 sensors can be connected via the terminal block (terminals C1 and C2).
NOTE
Looping of the 24V supply voltage (terminals 45/46)or also (terminals 44/40) is in
principle possible, however, a maximum current load of
2A for the SK CU4-DEV must not
be exceeded!
Detailed information about operation via DeviceNet can be found in the relevant supplementary manual
BU0280.
- www.nord.com
-
46 76 75 45 90 46 76 75 45 40 78 77 C2 C1 40 44
DEV-
DEV +
DEV-
DEV +
24V
GND
Sys+
Sys-
GND B
GND B
24V B
Incoming
DeviceNet cable
Outgoing
DeviceNet cable
Connection of the 24V supply volt-
age from the SK 200E
System bus connection
from the SK 200E
SHLD
Potential level: System bus
Potential level: Field bus
Connection to the
terminal block of the SK CU4-DEV
Similar to illustration