4. COMMISSIONING, USE AND MAINTENANCE
4.1. Reception, handling, storage
4.1.1. Equipment delivery
All the GVM motors are strictly controlled during manufacturing, prior to shipping.
Upon receipt it, it is necessary to verify the motor condition and confirm it has not been
damaged during transit. Remove it carefully from its packaging. Verify that the data written
on the label are the same as the ones on the acknowledgement of order, and that all
documents or necessary accessories for user are present in the packaging.
Warning : In case of damaged material during the transport, the recipient
must immediately make representations to the carrier through a
registered mail within 24 h.
4.1.2. Handling
The GVM motors are equipped with threaded holes on its housing for handling.
DANGER: Only use the threaded holes the GVM motors are equipped
with for handling operations. Never use cables, connectors, input/output of
cooling circuit, or any other inappropriate lifting device.
DANGER: Choose the correct slings for the motor weight. The two slings
must be the same length and a minimum angle of 50° has to be
respected between the motor axis and the slings.
50°min
i
50°min
i