PEDROLLO DG PED 3 - PRIMING PROCEDURE; Priming Operation Steps

PEDROLLO DG PED 3
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
25ENGLISH |
n
Unscrew and remove the lling plug and the vent plug.
o
Pour in about 1.5 litres of water until it pours out of the
vent hole.
p
Rescrew the lling plug and the vent plug.
q
Open the water tap
r
Attach the plug to the electricity supply.
s
Turn the switch to I”.
t
SIMULTANEOUSLY press buttons and for 5 seconds.
DG PED enters into a priming mode.
GREEN LEDS
FLASHING
RED LED
FIXED
u
Press button to start priming.
GREEN LEDS
FLASHING
GREEN LED
FLASHING
The priming procedure lasts at most 5 minutes, at the end of each minute DG PED automatically stops the electric pump
for ve seconds then immediately restarts it. This is repeated for all the time the DG PED is priming. During this procedure
the LEDS will continue to ash.
The exit from the priming procedure can occur either because of time out (5 minutes) or because it is completed. The
LEDS stop ashing. If the pump does not prime repeat the operation from the start.