Pulsar® Infinity Operation and Installation ManualWater Treatment 18
4.2 Startup Procedures
Warning - Higher than normal levels of chlorine may develop in-
side the feeder during extended periods of no flow through the
feeder. This may result in a higher than normal level of chlorine
injected into the pool when flow through the feeder is re-estab-
lished. To prevent this, drain the feeder prior to start-up after
extended periods of no flow through the feeder.
4.2.1 Feeder Startup
After completing the PRE-START-UP PROCEDURE, and establishing that
all components of the feeder are operating properly, your Pulsar® Infin-
ity Feeder is ready for start-up.
1. Establish the proper cartridge feed rate setting for your pool us-
ing the chart in section 4.2.2
2. Load the cartridge assembly with Pulsar® Infinity Tablets by fol-
lowing section 4.1.3.
3. Open the inlet and outlet ball valves at the pool piping.
4. Open the ball valve at the feeder inlet and set the flow meter to
the recommended feed rate setting determined in step 1 using
the ball valve at the feeder inlet.
NOTE: If using the optional ORP kit, follow instructions in section
4.2.3 to control feed rate.
5. Monitor the flow rate through the feeder daily to ensure that the
proper flow rate is being maintained.
6. During the first few days of operation, check the chlorine level in
the pool frequently to establish the best inlet flow rate and car-
tridge feed rate setting for your pool. Adjust the chlorine output
either up or down according to the table, or adjust the ORP set-
point if using the ORP kit.
4.1 Pre-Startup Procedure (continued)
4.1.3 Loading the cartridge assembly with Pulsar® Infinity
Tablets (continued)
Figure 19
Figure 20
Figure 21 Figure 22