Important information on spreading
93
10
10.3 Fertiliser spreading process
The intended use of the machine includes compliance with the operating, main-
tenance, and service conditions in accordance with the manufacturer specifica-
tions. Spreading operation therefore always includes preparation and
cleaning/maintenance.
Carry out spreading operations in accordance with the sequence described
below.
Preparation
Attach the spreader to the tractor Page 43
Close the metering slide
Pre-set the mounting height Page 47
Fill with fertiliser Page 56
Implement the calibration test Page 81
Set spreading vane Page 68
Set the application rate Page 60
Spreading
Travel to the spreading location
Check the mounting height
Engage the PTO shaft
Open the slide and start spreading
Finish spreading and close the slide
Disengage the PTO shaft
Discharge residual material Page 89
Cleaning/maintenance
Open metering slider
Remove the spreader from the tractor
Cleaning and maintenance Page 109