Reach PoE5 Tester Manual 1.8 03/25/2021 Page 40
B.7 Power Status and overload (IEEE 802.3bt, single signature)
PSE check after commands issued
reset
detect ok
single on
class 8
set 20
connect on
Enable power to port
Verify that PSE sees the device is taking power.
Verify that voltages are as expected.
Verify that PSE is providing full power.
Verify that PSE sees overload and shuts off
power.
Verify that power is off.
B.8 Power Status and overload (IEEE 802.3bt, dual signature)
PSE check after commands issued
reset
detect ok
single off
class 5
set 20
connect on
Enable power to port
Verify that PSE sees the device is taking power.
Verify that voltages are as expected.
Verify that PSE is providing full power.
Verify that PSE sees overload and shuts off
power.
Verify that power is off.