R&S ZVB Instrument Construction and Function Description
1145.1078.82 3.43 E-4
Replacing Receiver Board
(R&S ZVB4/8 only)
(See Chapter 5, Spare Parts List, Item 120, 125 and drawing 1302.4960.08)
Opening the instrument and removing the board
Remove the Reflectometer (see chapter Replacing a Reflectometer RM8 A510 to A540)
Remove the cover (150)
Pull off the Receiver Board (120, 125)
Installing the board and reassembling the instrument
Fit the new Receiver Board (120, 125)
Fit the cover (150)
Reinstall the Reflectometer (see chapter Replacing a Reflectometer RM8 A510 to A540)
Connect the mains cable and turn on at the mains switch. The instrument is now in the standby
mode
Select Service Level 2 (see Service Functions).
When the instrument has been started, check the protocol file for errors:
[ INFO : Error Log ]
Record the generator and receiver correction data (see Recording Correction Values).
Perform the factory system error calibration (see Factory System Error Calibration).