11.8 Assemble the equalizing cables.
1. Remove sheave cover, Fig. 32.
2 Refer to Fig. 34 for the general cable
arrangement. First, run a cable end up through
the small hole in the lower tie-off plate, Fig. 35.
3 Push the cable up until the stud is out of the
carriage top opening.
4 Run a nylon insert lock nut onto the cable stud so
13mm of the stud extends out of the lock nut.
5 Pull the cable back down, Fig. 35.
6 Run cable around the lower sheave, then up and
around overhead sheave and across and down
to the opposite carriage, Fig. 34. Install sheave
cover, Fig. 32.
7 Fasten the cable end to the carriage upper tie-off
bracket. Tighten the lock nut enough to apply light
tension to the cable.
8 Repeat procedure for the second cable. Adjust
the tension of both cables during the nal
adjustments in Chapter 12 commissioning.
Fig. 32 Detail
A Attach hose to column using 3/8-
16NC x 3/4" carriage bolts, flanged
lock nuts, and hose clips.
B Sheave Cover
Fig.32
Fig. 34 Detail
A Upper sheaves
B Cable 2
C Cable 1
D Lower sheaves
Fig. 33 Detail
A 3/8-16NC x 3/4" flanged HHCS and
flanged lock nut.
Fig. 35 Detail
A Upper cable tie-off plate and 5/8"
nylon insert lock nut.
B Lower cable tie-off and 5/8" nylon
insert lock nut.
C Steel pipe spacer for narrow bay and
low ceiling.
To set up cables for a low ceiling
(LC), use approximately 16mm
I.D. with a 3mm minimum wall
thickness steel pipe located at the
lower cable tie off. The lengths
required are as follows:
4" (102mm) Lower Height =
8" (203mm) long pipe
8-1/2" (216mm) Lower Height =
17" (432mm) long pipe
Fig.33
Fig.34
Fig.35