GAME TEST MODE
■ CONTROLS
- Press the SERVICE Button to select menu item.
- Press the TEST Button to conrm the selected item.
Operations can also be performed using the following input method.
×
Moves the arrow downward.
Moves the arrow upward.
,
Conrm the selected item.
- Select EXIT and press the TEST Button to return to the GAME TEST MENU screen.
■ MENU ITEMS
CONNECT TEST Performs a network connection test.
Normal if "STATUS OK" is displayed when test is performed. "STATUS NG" will be
displayed if there is a fault.
4-12 NETWORK TEST
Performs a test of network connection.
NETWORK TEST
CONNECT TEST
-> EXIT
SELECT WITH SERVICE BUTTON AND PRESS TEST BUTTON
NETWORK TEST screen
3
4
http://op.sega.jp/op_e/

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sega Future Tone ProjectDIVA Arcade and is the answer not in the manual?

Sega Future Tone ProjectDIVA Arcade Specifications

General IconGeneral
BrandSega
ModelFuture Tone ProjectDIVA Arcade
CategoryArcade Game Machines
LanguageEnglish

Related product manuals