7SR224 Argus Commissioning & Maintenance Guide
©2010 Siemens Protection Devices Limited Chapter 6 Page 36 of 73
2.9.1 Definite Time NPS Overcurrent (46DT)
If DTL setting is small, gradually increase current until element operates.
If DTL is large apply 0.9x setting, check for no operation, apply 1.1x setting, check operation
Apply 2x setting current if possible and record operating time
Phase Is
(Amps)
DTL
(sec)
P.U. Current
Amps
Operate Time
2 x Is
NOTES
NPS
Check correct indication, trip output, alarm contacts, waveform record.
2.9.2 Inverse Time NPS Overcurrent (46IT)
It will be advantageous to map the function being tested to temporarily drive the relevant Pickup output in the
Pickup Config sub-menu in the Output Config menu as this will allow the Pick-up led to operate for the function.
Gradually increase current until Pickup LED operates.
Apply 2x setting current and record operating time,
Apply 5x setting current and record operating time.
Compare to calculated values for operating times
Operate Current Operate Time
Ph. Char.
(NI EI VI LTI,
DTL)
Is
(A)
TM
P.U.
(Amps)
D.O.
(Amps)
2 x Is
(sec)
5 x Is
(sec)
NOTES
P.U.
D.O.
&
TIMING
TESTS
NPS
Calculated Timing values in seconds for TM =1.0
Curve 2 xIs 5 xIs
IEC-NI 10.03 4.28
IEC-VI 13.50 3.38
IEC-EI 26.67 3.33
IEC-LTI 120.00 30.00
ANSI-MI 3.80 1.69
ANSI-VI 7.03 1.31
ANSI-EI 9.52 1.30
Note that the operate time may be subject to the Minimum op time setting for the element and/or may have a
Follower DTL applied.