4.5 Commissioning the adjustment device
Securing the adjustment device to the detector
1.
From the adjustment set, take the chain with the two cable grippers and the
snap hook.
2.
Screw one cable gripper into a free opening for the cable entry(1) on the
detector base. Cable grippers are available in two different sizes:
PG16
M20x1.5
3.
Secure the snap hook on the suspension chain of the adjustment device(3).
a The adjustment device hangs on the detector. You therefore have your hands
free to undertake commissioning work.
Connecting the adjustment device
w The detector line is switched on.
1.
Connect the adjustment device(3) electrically to the detector. To do so, use the
MC link cable included in the scope of supply and the connecting sockets (2)
on the detector and on the adjustment device.
2.
Switch on the adjustment device with the button on the right (4). With the same
button, it is possible to switch between 'Adjust' and 'Initialization'.
4
3
2
1
Figure 21: Detector with adjustment device
1 Opening for cable entry 3 Adjustment device
2 Bushes 4 Button
Indication on the adjustment device
The indication before the initialization differs from that after initialization. The
indication is described in the table below.
Commissioning
Commissioning the adjustment device
4
A6V10332811_e_en_-- 25 | 44