EasyManuals Logo

Siemens PAD-5 Series User Manual

Siemens PAD-5 Series
40 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #38 background imageLoading...
Page #38 background image
1
Model PAD-5
Battery Size Calculations
Siemens Industry, Inc.
A6V101030358_en--_c
Smart Infrastructure
4 Battery Maintenance
Perform the following tests at the recommended interval. Replace the battery set
every four years or if any of the test criteria are not met.
Initiation / Reacceptance
1. Charger TestWith the batteries fully charged and connected to the charger,
measure the voltage across the battery set. It must read 27.3V +/- 0.3V.
2. Discharge TestWith full system alarm load, the voltage on a fully charged
battery must not fall below 20.4V after 30 minutes.
3. Load Voltage TestWith full system alarm load, the voltage on a fully charged
battery must not fall below 24.6V after one minute.
Testing Interval
1. SemiannuallyPerform the Load Voltage
Test.
2. AnnuallyPerform the Charger Test and
Discharge Test.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens PAD-5 Series and is the answer not in the manual?

Siemens PAD-5 Series Specifications

General IconGeneral
BrandSiemens
ModelPAD-5 Series
CategoryComputer Hardware
LanguageEnglish

Related product manuals