Section 4 – Pre-operation Function Tests
4.3 Function Tests
Function tests are designed to discover any
malfunctions before MEWP is put into service. The
operator must understand and follow step-by-step
instructions to test all MEWP functions.
WARNING
Never use a malfunctioning MEWP. If malfunctions
are discovered, MEWP must be tagged and taken
out of service. Repairs to MEWP may only be made
by qualied/competent repair personnel.
After repairs are completed, operator must perform a
pre-operation inspection and a series of function tests
again before putting MEWP into service.
Prior to performing function tests, be sure to read and
understand Section 5.1: Start Operation.
NOTE
All motion alarm should sound while activating
the footswitch.
4.3-1 Testing main power connectors
1. On the left side of the MEWP, disconnect and
lock out connector.
Result: MEWP functions should not operate.
2. Remove lock and plug in connector.
Result: Power to MEWP should be restored.
3. On the right side of the MEWP, disconnect and
lock out connector.
Result: MEWP functions should not operate.
4. Remove lock and plug in connector.
Result: Power to MEWP should be restored.
Main power
connectors
To order go to Discount-Equipment.com

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Skyjack SJ30 AJE and is the answer not in the manual?

Skyjack SJ30 AJE Specifications

General IconGeneral
BrandSkyjack
ModelSJ30 AJE
CategoryBoom Lifts
LanguageEnglish

Related product manuals