148
SJ30AJE, SJ30ARJE196274AF
Section 5 – Procedures Boom & Jib
33. One by one, remove the cylinder fitting caps
and reconnect the hoses (x4), lifting the riser if
needed to access the lower fitting.
Front Back
34. Lift the riser and main boom until the upper
cylinder pin hole is accessible.
35. Align the cylinder rod end with the pin holes
(use the riser lift/lower and/or platform up/down
functions to help align the holes), and tap the
original pin back in. Reinstall the keeper pin,
bolt and washer, applying Loctite 242 to the bolt
before installing it.
36. Remove the oil pan and clean up any leaked oil.
37. Remove the sling from the fly boom.
38. Raise the boom to provide clearance, then use
the platform level switch on the base controls to
fully raise and lower the platform 3 times.
39. Check for leaks at the master cylinder fittings and
hoses.