8 Commissioning the Inverter SMA America, LLC
56 SB30-40-US-IA-en-33 Installation Manual
8 Commissioning the Inverter
Always commission the inverter according to the following procedure.
Requirements:
The AC miniature circuit-breaker must be correctly rated.
All cables must be correctly connected.
The enclosure lid must be closed and correctly grounded.
1. Remove all covers from the PV array.
2. Switch on the AC miniature circuit-breaker.
3. Turn the rotary switch of the DC Disconnect to the
On position.
The start phase begins. The green LED blinks
3 times per second for 10 s.
The green LED glows and the inverter feeds into
the power distribution grid.
Is the green LED not glowing?
Observe LED signals and error messages in
the display, and rectify errors
(see Section 10 "Troubleshooting", page 63).