13 Decommissioning the Inverter
SMA Solar Technology AG
Operating ManualSTPx0-3SE-40-BE-en-10118
9. Unscrew and remove the antenna.
10. If there is a protective cap available, plug the protective cap onto the jack for connecting the
antenna.
11. Remove connector from COM socket.
12. Remove the swivel nut from the threaded sleeve.
13. Remove the terminal from the threaded sleeve.
14. Remove all conductors from the terminal points using
a screwdriver (blade width: 2.5mm).
15. Put the protective cap on the socket.
16. If an additional grounding or an equipotential
bonding is connected to the inverter, unscrew the
pan head screw M5x12 (TX25) and remove the
grounding cable.
17. Unscrew the left- and right-hand pan head screws M4x14 used to secure the inverter to the
wall mounting bracket (PH2).