8. Commissioning
8.1 Commissioning work
The following requirements must be fullled to carry out commissioning work and preparatory work must be completed.
Preconditions
Tool Material Protective equipment
none none none
Preparatory work
1. Completed installation with leak test
Picture
Description
Automatic drain Mechanically open
1. Turn the knurled-head screw on the
oat drain from >>mechanically open<<
counter-clockwise (left) to >>automatic
drainage<<
Picture Description
1 3 2
2. Slowly open the shut-o valve [1] on the
inlet side
3. Slowly open the shut-o valve [2] on the
outlet side
4. Close the shut-o valve [3] on the bypass
line