5 Electrical Connection User Manual
1. Strip the protection layer of the MPLC cable with a wire stripper. Stripped length are
as follows.
2. Install the pin on the MPLC cable after the protective layer has been removed, and
crimp the MPLC cable using crimping tools. Prepare three MPLC cables with pins.
3.
Connect the pins of the cables to the socket, as shown in the following figure.
Connection Method
Connect one end of the MPLC power cable in the scope of delivery to MPLC ports L1, L2,
and L3 of the Data Logger, and the other end to the three-phase ports of the circuit breaker.
The L1 port of the Data Logger must be connected to phase A of the circuit breaker, the L2
port to phase B, and the L3 port to phase C. The details are shown in the following figure.
26