When communications between battery and inverter does not exist, do not over-
charge your battery bank (current or voltage). Many lithium batteries are limited to
100A, some are lower and some are higher. Ensure that voltage and current speci-
fications provided by the battery manufacturer are followed.
If you are using lead acid batteries then follow the equation of C x 0.25 which means
that the maximum charge or discharge you can apply to a battery is a quarter of the
AH rating of the overall battery array. E.g: A 200Ah battery array composed of 4 x
200Ah batteries in series has a maximum discharge of only 50Ah (200 x 0.25 = 50)
Also, ensure the cable is thick enough to support the current and the fuses con-
nected are of the correct rating as per the recommendations of battery manufac-
turers.

Other manuals for SunSynk SUNSYNK-5K-SG01LP1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SunSynk SUNSYNK-5K-SG01LP1 and is the answer not in the manual?

SunSynk SUNSYNK-5K-SG01LP1 Specifications

General IconGeneral
BrandSunSynk
ModelSUNSYNK-5K-SG01LP1
CategoryInverter
LanguageEnglish

Related product manuals