EasyManuals Logo

SunSynk SUNSYNK-5K-SG01LP1 User Manual

SunSynk SUNSYNK-5K-SG01LP1
80 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #76 background imageLoading...
Page #76 background image
SINGLE PHASE HI 3.6/5kW | User Manual76
8. COMMISSIONING
8.1. Start-Up / Shutdown Procedure
The inverter must be installed by a qualied / licensed electrical engineer in accordance with the country's
wiring regulations.
Before switching on, the installation engineer must have completed the Earth Bond, RCD and earth leakage
tests, checked that the solar panel Voc voltage does not exceed 480V and checked the battery voltage.
Power ON Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator)
Shutdown Sequence:
1. Switch o AC
2. Press the start button
3. Switch o the battery and the battery breaker
4. Switch o the DC (PV isolator)
8.2. Information for Commissioning the Inverter
After you have successfully powered up the inverter, it must be programmed and set up as per the
programming feature above.
Check each bond on the
solar panels
Check the VOC does not
exceed 480V
Ensure both MPPTs are
balanced
Measure the supply volt-
age check it matches the
settings of the inverter
If it falls out of the setting
range it will cause the in-
verse shut down and alarm
See Grid Setup page
Check the battery charge
and discharge is within
the C rating of the battery.
Too high will damage the
battery
Check the battery BMS is
communicating with the
inverter

Table of Contents

Other manuals for SunSynk SUNSYNK-5K-SG01LP1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SunSynk SUNSYNK-5K-SG01LP1 and is the answer not in the manual?

SunSynk SUNSYNK-5K-SG01LP1 Specifications

General IconGeneral
BrandSunSynk
ModelSUNSYNK-5K-SG01LP1
CategoryInverter
LanguageEnglish

Related product manuals