MEC 2 MICROPROCESSOR ENGINE/GENERATOR CONTROLLER
PM056 Rev 6 05/10/15 Thomson Technology
47
8.3.5.5.NO LOAD TEST:
To allow a timed No Load Test of the engine/generator set while using
the AMF control application, a digital input contact from an external
timer must be programmed for NO LOAD Test (Refer to Section 9.5
for
programming details).
The sequence of operation for a No Load Test condition is as follows:
With the utility supply normal and the generator stopped, a no load
test sequence may be initiated by closing an external exercise
timer contact to the programmed digital input for No Load Test.
Once the external exercise timer contact closes, the engine will
start and come-up to normal operating speed and voltage. The
MEC will issue an alarm of a No Load Test condition. The
connected transfer switch will remain on the utility and the
generator will not transfer on load. Note: should the utility supply
fail, the generator will automatically transfer on load.
The engine will continue to run as long as the external exercise
timer contact remains closed.
Once the external exercise timer contact opens, the engine will
continue to run for its cooldown time as programmed, then it will
automatically stop.