P9 ASD Installation and Operation Manual 27
Startup and Test
Before turning on the ASD, ensure that:
R/L1, S/L2, and T/L3 are connected to the 3-phase input power.
U/T1, V/T2, and W/T3 are connected to the motor.
The 3-phase input voltage is within the specified tolerance.
There are no shorts and all grounds are secured.
All personnel are at a safe distance from the motor and the motor-driven equipment.
Use the following table to record any changed parameters for future reference.
Table 3. ASD Parameter Changes by Installer/Maintenance Personnel.
ASD ID__________Name:______________________Date:_______ Notes
Parameter
Number
Parameter Name
Default or
Previous
Setting
New Setting
Unit of
Measure
Note: Settings may also be recorded via Program Utilities Type Reset Save User Settings.