AC-SVX003A-EN
121
7. Testing
Dry nitrogen available for pressure testing
Trace gas amounts of refrigerant available for leak
testing, if necessary
8. Refrigerant on job site (if nitrogen charge option,
model number digit 16 = F, is chosen)
9. Systems can be operated under load conditions
10. Heaters
If unit was factory charged (model number digit 16
= E), energize heaters for 24 hours prior to start-up.
Important: Chiller heaters must be energized a
minimum of 24 hours prior to start-
up. Chiller should have power
applied for this amount of time
before Trane Service arrives for
start-up.
If unit has nitrogen charge (model number digit 16 =
F), contact Trane Service for unit charging prior to
start-up.
Important: Do NOT apply shore/service power to unit
with nitrogen charge. Shore/service power
will drive EXV valves, inhibiting ability to
adequately Vac and charge unit.
11. Owner Awareness
Does the owner have a copy of the MSDS for
refrigerant?
Note: Additional time required to properly complete the
start-up and commissioning, due to any
incompleteness of the installation, will be invoiced at
prevailing rates.
This is to certify that the Trane® equipment has been
properly and completely installed, and that the applicable
items listed above have been satisfactorily completed.
Checklist
completed by: ________________________________
Signed: ________________________________
Date: ________________________________
In accordance with your quotation and our purchase order
number __________________, we will therefore require
the presence of Trane service on this site, for the purpose
of start-up and commissioning, by __________________
(date).
Note: Minimum two-week advance notification is required
to allow scheduling of the chiller start-up.
Additional Comments/Instructions:
Note: A copy of this completed from must be submitted to
the Trane Service Office that will be responsible for
start-up of chiller.
Log and Check Sheets

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane Ascend ACR C Series and is the answer not in the manual?

Trane Ascend ACR C Series Specifications

General IconGeneral
BrandTrane
ModelAscend ACR C Series
CategoryChiller
LanguageEnglish

Related product manuals