1 Introduction to VESDA-E VEA Commissioning ................................................................................. 1
2 The Commissioning Process ............................................................................................................... 2
2.1 Pre-Commissioning (before going to site) ............................................................................... 2
2.2 Pre-Commissioning (on site) ..................................................................................................... 2
2.3 Configuration ............................................................................................................................... 3
3 NFPA72 Code Compliance ................................................................................................................... 4
3.1 NFPA72 Requirements ............................................................................................................... 4
4 Commissioning Tests ........................................................................................................................... 5
4.1 Initial Tests .................................................................................................................................. 5
4.2 Functional Tests .......................................................................................................................... 6
4.3 Smoke Tests ................................................................................................................................ 6
4.4 Walk Test...................................................................................................................................... 7
Annex A: VESDA-E VEA Configuration Record ........................................................................................... 8