iPM 200 generator module
® Vetaphone March 2021 3401201GB
Page 21 of 52
6 Checklist – Start up
GENERATOR:
1) Is the generator mounted at the desired location?
2) Is the mains cable supplied and connected correctly to terminal -X19
and does it carry the correct voltage?
Voltage and recommended prefuse, see cable drawing diagram.
3) Is the HA‑cable (do not shorten) connected correctly to terminal -X18?
4) Is the MULTI cable mounted correctly to terminal -X7?
5) Is the STATION cable connected correctly to terminal -X5?
6) Is the remote-control panel (if supplied) mounted and connected correctly to terminal -X6?