FILLING THE SYSTEM
1 Ensure all system and boiler drain points are
closed.
2 If connected to an open vented system turn
on the water supply to system header tank
and allow to fill the system.
3 For sealed systems fill the system using a
WRAS approved filling loop to a pressure of
1 bar.
4 Vent (A) any air from the boiler heat
exchanger using a suitable container to
collect any water. Ensure tube outlet (B) is
directed away from the fan or any other
electrical component to prevent any water
damage. Also place a suitable cover over
the fan to prevent any spillage of water onto
electrical connections. Ensure the cover is
removed after venting.
5 Vent all radiators and primary side of the hot
water cylinder.
GAS SUPPLY
Open gas cock on the boiler and purge the
gas supply to the boiler ensuring that the
room is well ventilated.
Test for gas supply for soundness as
described in BS 6891.
1
4
A
B
FILLING THE SYSTEM
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR Ri
8 716 109 699a (05/05)
27
COMMISSIONING

Other manuals for Worcester Greenstar Ri

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Worcester Greenstar Ri and is the answer not in the manual?

Worcester Greenstar Ri Specifications

General IconGeneral
TypeRegular
Fuel TypeNatural Gas
MountingWall-mounted
ERP RatingA
Central Heating Flow Temperature Range30°C to 80°C
Standard Warranty5 Years
Dimensions600 x 390 x 270 mm

Related product manuals