JOHNSON CONTROLS
101
SECTION 6 – COMMISSIONING
FORM 150.72-ICOM7
ISSUE DATE: 10/22/2020
6
FIGURE 28 - EEV IB-G INTERFACE BOARD
DIP SWITCH
NUMBER
YLAA0230
ALL OTHER
CHILLERS
1 OFF OFF
2 OFF ON
3 OFF OFF
DIP SWITCH
NUMBER
ALL
CHILLERS
4 OFF
5 OFF
6 ON
7 OFF
8 OFF
JUMP
LOCATION
INPUT
SIGNAL
1 0–10 V
Sporlan EEV Interface Board
Verify the jumper and dip switch settings, Figure 28
on page 101, during a chiller start-up for YLAA and
YCWL chillers with Sporlan Electronic Expansion
Valves.
With the IB-G unpowered, select the input signal of
0-10 V by installing the supplied jumper to number 1
of the 5 pin locations shown in the left hand side of
EEV board. Set numbers 1 to 3 of the DIP switches in
accordance with the unit models. Set numbers 4 to 8 in
accordance with the table shown in “Figure 36 - Con-
denser Fan Locations” on page 161. For YLAA and
YCWL chillers, DIP switch number 6 must be set to
ON for a quicker EEV response.
PREPARATION – POWER ON
Perform the commissioning using the
detailed checks outlined. Refer to Equip-
ment Pre-Startup And Startup Checklist
(Form 150.72-CL1) as the commissioning
procedure is carried out.
Apply power to the chiller. Turn on the option panel
circuit breaker if supplied.
The machine is now live!