7 - Operation
STEP 3 - Date, Time and Time zone
Set the Date, Time and Time zone (The inverter will propo-
se these elds when available).
When it’s not possible for the inverter to detect the time
protocol, these elds have to be manually entered.
Click on “Next” button to proceed to the next stage of the
conguration wizard.