7 - Operation
COMMISSIONING PROCEDURE - WIRELESS CONNECTED
Open an internet browser (recommended browser: Chrome versions from
v.55, Firefox versions from v.50, explorer is not compatible) and enter
the pre-set IP address 192.168.117.1 to access the Web User Interface.
Web User interface has easy commissioning wizard to commission the
inverter.
The language of the wizard could be changed by clicking on the upper status bar
The required informations during the procedure are:
STEP 1 - Administrator/User login credentials
-
Set the Administrator account user and password
(minimum 8 character for password):
Administrator account can open and view the contents
of photovoltaic site. Additionally, they can make changes
to inverter settings.
User and password are CASE SENSITIVE.
-
Set the User account user and (optional) password
(minimum 8 character for password):
User account can only read data. It cannot make any
changes.
User and password are CASE SENSITIVE.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB PVS-50-TL and is the answer not in the manual?

ABB PVS-50-TL Specifications

General IconGeneral
BrandABB
ModelPVS-50-TL
CategoryInverter
LanguageEnglish

Related product manuals