- 85 -
- 85 -
000196BG
7 - Operation
Installing the Wiring Box cover
When you have nished connecting and conguring the inverter, and
before you start it up, you must install the Wiring Box cover.
During installation of the cover, perform the operations listed in order and use the specied
torque for tightening the 6 screws (show in the technical data section) to maintain the in-
verter’s IP level
Insert the 6 anchoring screws and give them a few turns.
Then tighten the screws, following the order and torque shown.
6
1
3
2
4
5
When you have nished installing the Wiring Box cover you may start up
the inverter.