6. If there is a fourth switch, power it on and wait two minutes for it to join
the stack as a member with the ID number 4.
At this point, the stack is operational.
The ID numbers are automatically stored in special files in the flash
memories of the switches and are retained by the devices even if you
reset or power cycle the stack.
7. Secure the power cords to the switches by lowering the retaining clips.
See Figure 44.
Figure 44. Lowering the Retaining Clip
8. To continue with the installation, go to “Verifying the Stack” on
page 94.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Allied Telesis AT-GS948MX and is the answer not in the manual?

Allied Telesis AT-GS948MX Specifications

General IconGeneral
BrandAllied Telesis
ModelAT-GS948MX
CategorySwitch
LanguageEnglish

Related product manuals