1.4 Commissioning - Start Up Checklist
DO NOT connect power until you have gone through the
checklist below
• Arethewettedcomponentsresistanttothecorrosive
properties of the tank product?
• Doestheinformationgivenonthenameplatecorrespond
with the application?
• Exdapplications:Haveyouconnectedtheequipotential
bonding system correctly?
• Exiapplicatons:Areyouusingintrinsicbarrierwithin
the correct parameters?
• Didyouinstallcableentriesofthecorrectinternal
diameter so there is a good seal around the cable?
• Arethecableglandssuitablycertifiedperthe
application and the hazardous area parameters?
• Donotusetheearthterminalinthewiring
compartment; use the equipotential bonding system.