The right seeding shaft is selected and ready, see Selecting the right seeding
shaft On page 31 for more information.
Required components, tools and materials
For this work step, the following components, tools and materials are required:
Hexagon key
Overview
Access to the agitator drive and the required tool:
No. Designation
1 Bearing cover
2 Hexagon key holder
3 Cover nuts
4 Drive belt
5 Bearing flange
6 Knurled nuts
Procedure
This is how to change the seeding shaft:
Step Description Explanation
1 Take the hexagon key from the holder
(2).
2 Loosen the cover nuts (3) on the bear-
ing cover (1).

Table of Contents

Other manuals for APV PS 120 M1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the APV PS 120 M1 and is the answer not in the manual?

APV PS 120 M1 Specifications

General IconGeneral
BrandAPV
ModelPS 120 M1
CategorySeeders
LanguageEnglish

Related product manuals